Installation of protective casings for Khimki Electricity Networks at a transport interchange near the intersection of a road and a railway. The 1,200 m figure is the total project volume, not the length of a single crossing.

- Location
- Prospekt Mira, Khimki
- Client
- Borodino Group
- Scope
- Protective casings
- Pipe / casing diameter
- 160 mm
- Total installed length
- 1,200 m
- Recorded duration
- 10 days
Planning similar work?
Send the crossing plans and profiles, information about existing utilities, casing specifications and requirements of the infrastructure owners. We will also review equipment access and permitted working hours.
Engineering and delivery for your project
Our own team carries out the agreed site investigations, design, technical quality control and as-built documentation. We engage and coordinate specialist drilling crews with equipment suited to the task.
The scope for a new project is agreed in the proposal. Quantities and durations in this case describe completed work; a new programme and price depend on your site information.